|
|
|
|
|
|

|
|
Subjectivity
in Hazard Analysis
|
|
by
Felix Redmill
London, U.K.
|
|
Page: 1 | 2 | 3
|
|
Introduction
This is the second in a series of three articles
on the subjective aspects of risk analysis. In
the first, published in the premiere
issue of eJSS (February 2003), risk
analysis was defined as comprising four stages
— scope definition, hazard identification,
hazard analysis, and risk assessment. In the first
stage, the scope and terms of reference of the
analysis are defined. In the second, the hazards
that could lead to breaches of safety are identified.
In the third, the risks associated with the hazards
are determined, and in the fourth the tolerability
of each risk is assessed against predetermined
criteria.
In considering the subjectivity in risk analysis,
the previous article particularly addressed the
first and second stages and briefly discussed
the fourth. This article examines the subjectivity
inherent in the third, hazard analysis, stage.
Once the scope and terms of reference of a risk
analysis have been defined, the second stage,
hazard identification, lays the technical foundation
of the analysis. It cannot be guaranteed that
all possible hazards are uncovered, or that all
hazards that will be discovered are identified,
as it would be extraordinary if further hazards
were not revealed later. But the coverage of later
analysis is constrained by the thoroughness of
the identification process: hazards not identified
are neither analyzed nor mitigated.
Given that risk is taken to be a function of probability
and consequence, hazard analysis, the third stage
of risk analysis, involves determining these two
parameters, which may be done quantitatively or
qualitatively, depending on the information available
and the confidence that can be placed in numeric
values. One method is to carry out a bottom-up
analysis, starting with each hazard and working
forwards towards its system-level consequences.
The initial effect of a hazard (e.g., the failure
of a component or person) may be local, but the
hazardous effect of interest is almost always
at the system level — i.e., at the boundary
between the system and "the rest of the world."
A second method of hazard analysis is to take
a top-down approach, commencing with the top hazardous
events and working backwards towards ultimate
causes, creating fault trees in which successive
causal events are identified.
The two approaches are complementary, and neither
is likely to offer a complete analysis. Because
their results are usually inconsistent in many
respects, they should be compared and integrated.
Yet, far from comparing them, some modern computer-based
tools automatically derive fault trees from the
results of a bottom-up technique such as FMEA
(failure modes and effects analysis). Naturally,
it can then be claimed that the fault tree is
consistent with respect to the model produced
from the FMEA. But, being the result of human
judgment, that model is almost certainly neither
complete nor wholly correct. Moreover, the opportunity
for cross-checking between bottom-up and top-down
methods is lost, and there is likely to be misplaced
confidence in the correctness of the fault trees.
The results of a risk analysis depend on the techniques
employed, the ways in which they are used, and
the consistency with which they are used with
respect to each other, all of these factors being
subjects of human discretion.
The more sophisticated hazard identification techniques,
such as hazard and operability studies (HAZOP)
and FMEA, also include bottom-up hazard analysis.
Discussion of these, and the subjectivity implicit
in their use, has already been provided [Ref.
1] and will not be repeated here. In examining
subjectivity in hazard analysis, this article
first considers the two aims of the process: to
determine consequences and likelihood. It examines
the ways in which subjectivity affects the numbers
arrived at in both cases. Then it considers the
use of the most usual top-down method, fault tree
analysis (FTA), in arriving at them. Finally,
there is a discussion of the findings.
|
"Not
only is there a degree of uncertainty about a
potential future event, there is also error, inaccuracy,
and the use of discretion and judgment in the
description and valuation of what might occur."
|
|
Consequences
At first glance, evaluating consequences may seem
objective, but what we evaluate depends on where
we look, and this is determined by a number of
decisions.
First, the consequences to be evaluated depend
on which event in a chain of events is considered
to be "final" or of interest in the
circumstances. For example, in transport a human
or component failure might lead to the loss of
control of a vehicle, which could lead to an accident,
which in turn could lead to a loss of life. Each
of these might be of interest as a "final
event," depending on the purpose of the risk
analysis, and each carries different assumptions
and a different probability of occurrence. Railtrack's
safety management manual [Ref. 2] takes loss of
life to be of interest, but the motor industry's
guidelines [Ref. 3] focus on controllability (or
loss of it) of the vehicle.
It must also be decided, at the scope-definition
stage of the analysis, whether estimations should
be based on the worst possible consequence, the
worst credible, or the most likely, and the risk
values are influenced by the choice. Further,
each scenario is not clearly defined and waiting
to be measured, but is a potential outcome whose
parameters must be subjectively defined — perhaps
in line with the goals or mind-set of a particular
industry sector.
Then, the values of the possible losses need to
be identified and estimated, and they may be distorted
in a number of ways. For example, some costs,
such as those of damage limitation and of cleaning
up after an incident, are frequently omitted.
Further, when there is no previous experience
of the hazardous event, it is easy to over- or
under-estimate the consequences. For example,
in the U.K., the losses attributed to a "hundred-year"
flood are now found to be a great deal higher
than previously assumed. Then there is the potential
to induce distortions by deliberate adjustments
of costs or benefits. There is also the problem
of putting prices on non-marketed goods. Marketed
goods carry known or agreed prices, and their
loss or replacement can be valued uncontentiously.
But non-commodities, such as human life, reputation,
and environmental loss or degradation, are not
so easily costed, and their valuation is necessarily
subjective.
Thus, there is always subjectivity in the estimation
of consequences, and more so when there is little
or no experience of the hazardous event. Not only
is there a degree of uncertainty about a potential
future event, there is also error, inaccuracy,
and the use of discretion and judgment in the
description and valuation of what might occur.
|
|
NEXT
PAGE
|
|
|
|
|

|
|
|